Works update – autumn 2013

Development update - October 2013Residents can now see positive progress as the regeneration of this phase moves forward.

The demolition is 90% complete and the next phase of construction is well underway (see photo).

The first properties completed will provide new shops and a temporary community hall.

The hall will be in use until a permanent hall can be provided in the following phase of construction post 2015.

The first homes completed will be mainly apartments with houses following on shortly afterwards.

The whole of the current phase is due to be completed during 2015.